Country for PR: United States
Contributor: PR Newswire New York
Wednesday, March 27 2019 - 18:00
AsiaNet
Peabody Releases Initial Learnings From North Goonyella Incident
ST. LOUIS, March 27, 2019 /PRNewswire-AsiaNet/ --

Peabody (NYSE: BTU) today released initial learnings from the North Goonyella 
mine fire that began in the third quarter of 2018.  Learnings are based on the 
company's comprehensive review of the events surrounding the incident, which 
included the mine general manager's required investigation report prepared in 
accordance with Section 201 of the Queensland Coal Mining Safety and Health Act 
of 1999.  

"When the serious incident at North Goonyella occurred, Peabody committed to 
sharing learnings for the benefit of our operations, our stakeholders and 
others in the industry," said Peabody President and Chief Executive Officer 
Glenn Kellow.  "We believe that the beginning of the planned reventilation and 
re-entry activities warrant a sharing of our initial learnings at this point.  
We are taking multiple actions to integrate these learnings into our practices 
at North Goonyella and our other operations, where appropriate.  The goal here 
is clear, to reduce the risk of such an event reoccurring at North Goonyella or 
any of our other mines in the future."  

In early September, high gas levels caused the evacuation of personnel at North 
Goonyella during a planned longwall move from the 9 North panel to the 10 North 
panel.  Subsequently, elevated carbon monoxide detected from within the mine 
indicated oxidation of coal, which can occur when coal is exposed to oxygen for 
an extended time period.  Over a number of weeks, the company worked together 
with industry experts, and in consultation with the Queensland Mines 
Inspectorate (QMI), to take extensive steps to treat the oxidation from the 
mine surface.  Actions were ultimately unsuccessful, and a fire occurred in 
late September.  

The company's review of the incident concluded that areas of the mine 
demonstrated both elevated methane levels and elevated carbon monoxide levels 
following completion of coal production in the 9 North panel.  During the 
longwall move sequence, a change in gas management focus to reduce elevated 
methane levels in the 9 North panel, including changes to the mine's 
ventilation system to increase airflow, inadvertently intensified the oxidation 
of coal that was likely causing elevated carbon monoxide levels.  

Despite sustained efforts to manage the oxidation from the mine surface, 
including use of nitrogen to create an inert environment within the 9 North 
panel goaf (the mined-out area in the panel), the oxidation accelerated into a 
spontaneous combustion event that eventually resulted in the fire.

Safety remains Peabody's number-one priority and its first value.  As a result 
of the actions taken to evacuate personnel in advance of the fire and other 
controls in place, the incident did not result in injury to any person.  
Throughout the incident Peabody's incident management team worked alongside the 
QMI and industry experts to ensure it utilized the best people and resources.  
Peabody continues to cooperate fully with the QMI as it undertakes its own 
independent investigation into the incident.

President - Australian Operations George Schuller said, "While this was a 
highly unusual combination of events, Peabody is making changes in systems, 
processes and training, where warranted, to put into place the improvements 
needed to successfully move forward from this incident.  For example, we have 
already begun installing remote control ventilation systems at mine 
entrances."  

It is the company's intent that longwall production at North Goonyella will not 
recommence until all necessary modifications are undertaken.  Peabody's base 
case that targets limited continuous-miner volumes in 2019 with longwall 
production beginning to ramp up in early 2020 remains unchanged with 
approximately 2 million tons of sales from North Goonyella in 2020.  Peabody 
continues to progress the execution of the multi-phased reventilation and 
re-entry of the mine in consultation with the QMI.

"I want to thank Peabody employees, the union, customers, neighboring mines, 
the community of Moranbah, the Inspectorate and countless others who have 
helped out during this challenging time," said Schuller.  "We will be 
contacting other coal companies and industry bodies to further share learnings 
in coming months to strengthen the body of knowledge around underground mine 
ventilation and fire prevention."  

Peabody (NYSE: BTU) is the leading global pure-play coal company and a member 
of the Fortune 500, serving power and steel customers in more than 25 countries 
on six continents. The company offers significant scale, high-quality assets, 
and diversity in geography and products. Peabody is guided by seven core 
values: safety, customer focus, leadership, people, excellence, integrity and 
sustainability.  For further information, visit www.PeabodyEnergy.com.  

                           Forward-Looking Statements

This press release contains forward-looking statements within the meaning of 
the securities laws. Forward-looking statements can be identified by the fact 
that they do not relate strictly to historical or current facts. They often 
include words or variation of words such as "expects," "anticipates," 
"intends," "plans," "believes," "seeks," "estimates," "projects," "forecasts," 
"targets," "would," "will," "should," "goal," "could" or "may" or other similar 
expressions. Forward-looking statements provide management's current 
expectations or predictions of future conditions, events or results. All 
statements that address operating performance, events or developments that we 
expect or anticipate will occur in the future are forward-looking statements. 
They may include estimates of revenues, income, earnings per share, cost 
savings, capital expenditures, dividends, share repurchases, liquidity, capital 
structure, market share, industry volume, or other financial items, 
descriptions of management's plans or objectives for future operations, or 
descriptions of assumptions underlying any of the above. All forward-looking 
statements speak only as of the date they are made and reflect the company's 
good faith beliefs, assumptions and expectations, but they are not guarantees 
of future performance or events. Furthermore, the company disclaims any 
obligation to publicly update or revise any forward-looking statement, except 
as required by law. By their nature, forward-looking statements are subject to 
risks and uncertainties that could cause actual results to differ materially 
from those suggested by the forward-looking statements. Factors that might 
cause such differences include, but are not limited to, a variety of economic, 
competitive and regulatory factors, many of which are beyond the company's 
control, that are described in our Annual Report on Form 10-K for the fiscal 
year ended Dec. 31, 2018, as well as additional factors we may describe from 
time to time in other filings with the SEC. You may get such filings for free 
at our website at www.peabodyenergy.com.  You should understand that it is not 
possible to predict or identify all such factors and, consequently, you should 
not consider any such list to be a complete set of all potential risks or 
uncertainties.

Discussion of Key Initial Learnings

As a result of Peabody's comprehensive review, the company has developed 
initial learnings and steps to improve the longwall move process and other 
mining activities.  

A)      Peabody will review ventilation controls and design used during the 
        longwall "take-off" process to minimize the amount of air that enters 
        the longwall panel goaf and interacts with exposed coal remaining 
        within the goaf.  Ventilation controls that were put into place in 
        advance of the longwall take-off process may have permitted higher-than-
        expected volumes of ventilation air to enter the goaf during the 
        longwall take-off process, resulting in oxidation.  Gas management and 
        ventilation changes were made in and around the 9 North panel tailgate 
        area in response to elevated levels of methane, which inadvertently 
        intensified the oxidation.  

B)      Evaluate decision-making processes to address the challenges of 
        remotely managing an underground incident solely from the surface, 
        which can lead to unclear or ambiguous results.  For instance, as the 
        incident approached late September and treatment of the oxidation event 
        escalated, including injection of nitrogen from the mine surface into 
        the 9 North panel goaf, fluctuating gas readings led North Goonyella 
        mine personnel and expert third-parties to believe that the treatment 
        plan was likely working due to a purging of gases from the goaf.

C)      Peabody also believes that the system used to monitor and analyze 
        available mine gas data can be improved and better coordinated to 
        identify early stages of oxidation events.  Additional training to the 
        appropriate mine personnel will be implemented to recognize fire gas 
        indicators, gas management and spontaneous combustion, and provide an 
        understanding of a mine's ventilation history, with focus on 
        identifying ventilation trends and key indicators of oxidation and 
        developing heating for longwall mines.

D)      Peabody will modify the longwall removal planning process to reduce the 
        number of days to complete the longwall take-off process to allow for 
        earlier commencement of final sealing, incorporating additional 
        contingency planning in the event the target cannot be achieved.  The 
        amount of time the North Goonyella mine's 9 North panel was idle 
        increased the propensity for oxidation to occur in the longwall panel 
        goaf.  Peabody will consider additional contingency measures, including 
        installation of pre-drilled holes at the appropriate locations 
        immediately behind the longwall chock line to allow oxygen inhibitors 
        to be injected when longwall advance stops to mitigate against 
        oxidation.

E)      Peabody will improve the Sealing Management Plan to provide greater 
        clarity around the required steps for sealing the longwall panel 
        (particularly in relation to how these steps interact and relate to the 
        longwall move and re-installation plan).  The improved plan will 
        provide for the allocation of resources to ensure the Sealing 
        Management Plan is followed as described.  Peabody will also provide 
        additional training for underground personnel prior to sealing 
        operations commencing. 

F)      Peabody will hone its system for the management of Trigger Actions 
        Response Plans (TARPs) to provide clearly defined trigger points, clear 
        explanations of actions to be taken if trigger levels are reached, and 
        improved methods, training and communications involving changing 
        TARPs.  Application and progression of TARPs during the longwall take-
        off process varied from that set out in the Sealing Management Plan, 
        and communication of TARPs was found to be inconsistent.  TARPs 
        describe actions that must be taken by mine personnel in response to 
        observation of certain conditions or triggers (e.g. gas levels) that 
        deviate from normal.  TARPs should clearly define their applicability 
        and the required action items when trigger points are reached. 

G)      Peabody will review the Principal Hazard Management Plan (PHMP) for 
        Spontaneous Combustion and Emergency Response around the provision of 
        clear and concise guidance in relation to gas readings.  The company 
        will also implement a regime for reviewing the PHMP at established 
        intervals and updating as required. 

H)      Within the Site Incident Management Team (SIMT), Peabody will appoint 
        an independent facilitator whose role will be to assist the SIMT in the 
        decision-making process (rather than the technical aspects of SIMT 
        decisions).  The SIMT was comprised primarily of North Goonyella mine 
        management personnel, though various other parties also provided input 
        into the SIMT's decision making process.  At times, it was challenging 
        for the SIMT to coordinate and address differing viewpoints from 
        multiple stakeholders.  Although these outside parties each play 
        critical roles in responding to a mine emergency, the varied viewpoints 
        need to be effectively managed and facilitated during an incident.

I)      Peabody is taking action to install quickly closable remote ventilation 
        control devices at each mine drift as we progress through the 
        reventilation process.  In addition, Peabody will evaluate options to 
        remotely isolate portions of the longwall panel to provide an option to 
        quickly close these devices after all personnel have been evacuated 
        from the panel.  Peabody's ability to quickly seal the panel to 
        extinguish the oxidation event before it developed into a fire was 
        impaired once the mine was evacuated and exclusion zones were put in 
        place.  Once an oxidation event develops into a spontaneous combustion 
        event, it is difficult to extinguish from the mine surface.  The 
        smaller the area of the mine that is sealed from the source of 
        combustion, the less oxygen is available to support it and the quicker 
        it begins to cool, which should facilitate expeditious recovery.  These 
        types of devices could be closed by personnel as part of an evacuation 
        sequence, or through remote means.  Emergency seals, which can be 
        installed at chute and gate roads at longwall panels, will also be 
        considered as part of an emergency sealing process.

Media Contacts:
Corporate
Michelle Constantine
+1 314.342.4351

Australia
Kellie Schneider
61 7 3333 5670

Investor Contact:
Julie Gates
+1 314.342.4336

Logo - https://mma.prnewswire.com/media/133191/peabody_energy_logo.jpg 

SOURCE: Peabody